Two steps: save, then approve
| Step | What happens to stock |
|---|---|
| Save the journal | Nothing. The journal exists and is Unapproved |
| Approve the journal (the quality check) | The raw materials go out, the approved finished goods and the by-products come in |
This differs from a sale or a purchase, which move stock when saved. A journal that is not approved has not changed your stock, and the Stock summary does not show its goods.
Record a journal
Open Production Journal (menu Production Entries › Production Journal, usual label).
- Choose Add
- Choose the production order
- Enter the quantities
- Check the raw materials
- Check fixed costs and by-products
- Save
What the screen checks
| Message | Cause |
|---|---|
| Please provide valid production quantity of goods going to produce. | Production QTY is 0 or less |
| Please select machine/plant to proceed production process. | No Machine / Plant |
| Raw material stock is not sufficient | A raw material line takes more than the warehouse holds |
| Raw material stock with zero cost value not allowed | A raw material has no cost, and your company does not allow zero-cost raw material |
| Raw material stock with negative cost not allowed | A raw material has a negative cost |
| Enter serial number details of product to proceed. / Please enter batch details for batch wise raw material / Please enter batch info for batch wise finished goods | Tracked products need their numbers or batches |
| Raw material stock is not available to proceed production journal. | The BOM has no raw materials |
| The financial year for this transaction date has already been closed… | The date is before the fiscal year starts |
Approve: the quality check
Open the journal and choose Approve. The box is titled Production quality check and approval and says that after this step the inventory and financial effects cannot be reverted. In this release approval changes stock only: no ledger entry is made (see below), and the stock can still change afterwards.
| Field | Meaning |
|---|---|
| Approved QTY | The quantity that meets your sales quality standard. It starts as the Production QTY |
| Rejected QTY | Production QTY less Approved QTY; worked out for you |
| Damaged serial no | For serial-number products, the numbers of the rejected units: as many as the rejected quantity |
| Notes | Optional |
Type Approve to proceed. "Production journal approved successfully." Now:
- the raw materials leave their warehouses;
- the Approved QTY of the finished product comes into the journal's warehouse, valued at the total cost shared over the Production QTY;
- the by-products come in.
If the Approved QTY is more than the Production QTY: "You entered quantity more than produced quantity."
| Area | Change |
|---|---|
| Raw materials | Each raw-material line's quantity leaves its warehouse on the journal date; it is valued at first-in-first-out cost when values are next worked out |
| Finished goods | The Approved QTY comes into the journal's warehouse at the journal's cost per unit (raw materials plus fixed costs, less by-products, over the Production QTY) |
| Rejected quantity | Never enters stock: its share of the cost is lost, which lowers the stock value |
| By-products | Come in at their quantity and costing |
| Fixed costs | Used in the cost per unit only; no expense or ledger entry is posted |
| Ledgers | Nothing. Profit changes through closing stock (Closing stock in the profit and loss, the balance sheet and the year end) |
| Production order | Nothing more: the journal's Production QTY already counted against the order when the journal was saved. The order's status stays Approved |
Edit and delete
Edit is always offered, even after approval, and so is Delete unless your company has IRD switched on. Deleting a journal takes its stock entries out. Pressing Approve again writes the stock again from the journal as it is now (the old entries are replaced, not doubled).
Common questions
We saved the journal but the finished goods are not in stock.
The journal is not approved yet. Approve it (What production changes in stock and in the books).
Raw materials are out but nothing came in.
The Approved QTY was 0, or the journal was edited after approval and not approved again.
Zero cost raw material is refused.
Your company switched off Allow production with zero rate raw material in Configuration. Give the raw material a cost, or ask your administrator (Set up production).
Can I produce more than the order?
Penahak does not stop you on the journal. The order list offers an order only while it has quantity left (the order's quantity less the journals already made from it), but the journal accepts any quantity. Filter the Production journal list by the order number to see what was already made, then save.